[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909118":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909118,587,1,"单选题","下列方法中，可同时用来控制工程造价和工程进度的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","S曲线法和直方图法",false,{"key":16,"text":17,"correct":14},"B","直方图法和鱼刺图法",{"key":19,"text":20,"correct":14},"C","鱼刺图法和香蕉曲线法",{"key":22,"text":23,"correct":24},"D","香蕉曲线法和S曲线法",true,"2020版教材P103 S曲线可用于控制工程造价和工程进度。与S曲线法相同，香蕉曲线同样可用来控制工程造价和工程进度。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]