[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909117":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},909117,587,1,"单选题","施工总进度计划的编制步骤包括①计算工程量，②确定各单位工程的施工期限，③确定各单位工程的开竣工时间和相互搭接关系，④编制初步施工总进度计划。这些工作正确顺序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①—②—③—④",true,{"key":16,"text":17,"correct":18},"B","②—③—①—④.",false,{"key":20,"text":21,"correct":18},"C","①—③—②—④",{"key":23,"text":24,"correct":18},"D","①—④—③—②","2020版教材P90 施工总进度计划的编制步骤包括①计算工程量，②确定各单位工程的施工期限，③确定各单位工程的开竣工时间和相互搭接关系，④编制初步施工总进度计划，⑤编制正式的施工总进度计划。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]