[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909115":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909115,587,1,"单选题","下列不属于工程项目建设总进度计划的表格是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程项目一览表",false,{"key":16,"text":17,"correct":14},"B","投资计划年度分配表",{"key":19,"text":20,"correct":14},"C","工程项目进度平衡表",{"key":22,"text":23,"correct":24},"D","年度计划项目表",true,"2020版教材P85 本题考查的是工程项目计划体系。工程项目建设总进度计划的表格部分包括工程项目一览表、工程项目总进度计划、投资计划年度分配表和工程项目进度平衡表。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]