[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909107":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},909107,587,1,"单选题","单位工程施工进度计划的编制工作包括：①计算工程量，②划分工作项目，③确定施工顺序，④计算劳动量和机械台班数，正确的程序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①—②—③—④",false,{"key":16,"text":17,"correct":18},"B","②—③—①—④",true,{"key":20,"text":21,"correct":14},"C","①—③—②—④",{"key":23,"text":24,"correct":14},"D","①—④—③—②","2020版教材P94 单位工程施工进度计划的编制程序：①划分工作项目；②确定施工顺序；③计算工程量；④计算劳动量和机械台班数；⑤确定工作项目的持续时间。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]