[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909104":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},909104,587,1,"单选题","下列措施中属于被动控制措施的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","编制计划的时候留有余地",false,{"key":16,"text":17,"correct":14},"B","进行风险识别和风险评价",{"key":19,"text":20,"correct":21},"C","根据偏差采取相应纠偏措施",true,{"key":23,"text":24,"correct":14},"D","制定必要的备用方案","2020版教材P100 被动控制可以采取以下措施：（1）应用现代化管理方法和手段跟踪、测试、检査工程实施过程，发现异常情况，及时釆取纠偏措施。（2）明确项目管理组织中过程控制人员的职责，发现情况及时采取措施进行处理。（3）建立有效的信息反馈系统，及时反馈偏离计划目标值的情况，以便及时采取措施予以纠正。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]