[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909077":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},909077,587,1,"单选题","下列关于CM(Construction Management)承包模式的说法中，正确的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","CM单位直接与分包单位签订分包合同",false,{"key":16,"text":17,"correct":14},"B","CM单位不负责工程分包的发包，与分包单位的合同由建设单位直接签订",{"key":19,"text":20,"correct":21},"C","CM承包模式使工程项目实现有条件的“边设计、边施工”",true,{"key":23,"text":24,"correct":14},"D","快速路径法施工并不适合CM承包模式","2020版教材P79 CM承包模式是指由建设单位委托一家CM单位承担项目管理工作，该CM单位以承包单位的身份进行施工管理，并在一定程度上影响工程设计活动，组织快速路径的生产方式，使工程项目实现有条件的“边设计、边施工”。CM单位有代理型和非代理型两种。代理型的CM单位不负责工程分包的发包，与分包单位的合同由建设单位直接签订。而非代理型的CM单位直接与分包单位签订分包合同。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]