[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909064":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},909064,587,1,"单选题","为了实现工程造价的模拟计算和动态控制，可应用建筑信息建模（BIM）技术，在包含进度数据的建筑模型上加载费用数据而形成（ ）模型。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","6D",false,{"key":16,"text":17,"correct":18},"B","5D",true,{"key":20,"text":21,"correct":14},"C","4D",{"key":23,"text":24,"correct":14},"D","3D","2020版教材P71 3）模拟施工。应用BIM技术，可根据施工组织设计在3D建筑模型的基础上加施工进度形成4D模型模拟实际施工，从而通过确定合理的施工方案指导实际施工。此外，还可进一步加载费用数据，形成5D模型，从而实现工程造价的模拟计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]