[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-909014":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},909014,587,1,"单选题","合同订立过程中，属于要约失效的情形是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","承诺通知到达要约人",false,{"key":16,"text":17,"correct":14},"B","受要约人依法撤销承诺",{"key":19,"text":20,"correct":14},"C","要约人在承诺期限内未做出承诺",{"key":22,"text":23,"correct":24},"D","受要约人对要约内容做出实质性质变更",true,"2020版教材P47 有下列情形之一的，要约失效：①拒绝要约的通知到达要约人；②要约人依法撤销要约；③承诺期限届满，受要约人未做出承诺；④受要约人对要约的内容做出实质性变更。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]