[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908955":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908955,587,1,"单选题","根据《合同法》，执行政府定价或政府指导价的合同时，对于逾期交付标的物的处置方式是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","遇价格上涨时，按照原价格执行；价格下降时，按照新价格执行",true,{"key":16,"text":17,"correct":18},"B","遇价格上涨时，按照新价格执行；价格下降时，按照原价格执行",false,{"key":20,"text":21,"correct":18},"C","无论价格上涨或下降，均按照新价格执行",{"key":23,"text":24,"correct":18},"D","无论价格上涨或下降，均按照原价格执行","2020版教材P53 《合同法》规定，执行政府定价或政府指导价的，在合同约定的交付期限内政府价格调整时，按照交付时的价格计价。逾期交付标的物的，遇价格上涨时，按照原价格执行；价格下降时，按照新价格执行。逾期提取标的物或者逾期付款的，遇价格上涨时，按照新价格执行；价格下降时，按照原价格执行。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]