[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908865":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908865,587,1,"单选题","在我国境内进行的大型基础施工工程建设项目，可以不进行招标的环节是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工",false,{"key":16,"text":17,"correct":14},"B","监理",{"key":19,"text":20,"correct":14},"C","勘察设计",{"key":22,"text":23,"correct":24},"D","可行性研究",true,"2020版教材P34 招标投标法规定，在中华人民共和国境内进行下列工程建设项目包括项目的勘察、设计、施工、监理以及与工程建设有关的重要设备、材料等的采购，必须进行招标",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]