[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908848":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},908848,587,1,"单选题","某项目中建筑安装工程费用为560万元，设备和工、器具购置费工为330万元，工程建设其他费用为133万元，基本预备费为102万元，涨价预备费55万元，建设期贷款利息为59万元(没有固定资产投资方向调节税)，则静态投资为（）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1023",false,{"key":16,"text":17,"correct":18},"B","1125",true,{"key":20,"text":21,"correct":14},"C","1180",{"key":23,"text":24,"correct":14},"D","1939","建设项目静态投资包括建筑工程安装费用，设备和工、器具购置费，工程建设其他费用，基本预备费，560+330+133+102=1125（万元）。2020教材P3",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]