[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908838":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908838,587,1,"单选题","建设项目工程造价的组合过程是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分部分项工程单价→单位工程造价→单项工程造价→建设项目总造价",true,{"key":16,"text":17,"correct":18},"B","单位工程造价→分部分项工程单价→单项工程造价→建设项目总造价",false,{"key":20,"text":21,"correct":18},"C","分部分项工程单价→单项工程造价→单位工程造价→建设项目总造价",{"key":23,"text":24,"correct":18},"D","单项工程造价→分部分项工程单价→单位工程造价→建设项目总造价","2020版教材P2 本题考查的是工程造价及其计价特征。工程造价的组合过程是：分部分项工程单价→单位工程造价→单项工程造价→建设项目总造价。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]