[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908793":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908793,587,1,"单选题","下列（ ）属于工程造价控制的经济措施。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","明确项目组织机构",false,{"key":16,"text":17,"correct":14},"B","重视设计多方案的比选",{"key":19,"text":20,"correct":21},"C","动态比较造价的计划值和实际值",true,{"key":23,"text":24,"correct":14},"D","严格审查施工图设计","2020版教材P6 本题考查的是工程造价管理的主要内容及原则。技术与经济相结合。要有效地控制工程造价， 应从组织、技术、经济等多方面采取措施。从组织上采取措施，包括明确项目组织结构，明确造价控制人员及其任务，明确管理职能分工；从技术上采取措施，包括重视设计多方案选择，严格审查初步设计、技术设计、施工图设计、施工组织设计，深入研究节约投资的可能性;从经济上采取措施，包括动态比较造价的计划值与实际值，严格审核各项费用支出，采取对节约投资的有力奖励措施等。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]