[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908774":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908774,587,1,"单选题","全要素造价管理的核心是按照优先性的原则，协调和平衡（ ）之间的对立统一关系。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工期、质量、安全、环保与成本",true,{"key":16,"text":17,"correct":18},"B","人工费、材料费、施工机具使用费与成本",false,{"key":20,"text":21,"correct":18},"C","直接成本、间接成本、规费、利润与成本",{"key":23,"text":24,"correct":18},"D","建筑安装工程费用、设备工器具费用、工程建设其他费用与成本","2020版教材P4 本题考查的是工程造价管理的基本内涵。控制建设工程造价不仅仅是要控制建设工程本身的建造成本，还应同时考虑工期成本、质量成本、安全与环境成本的控制，从而实现工程成本、工期、质量、安全、环境的集成管理。全要素造价管理的核心是按照优先性的原则，协调和平衡工期、质量、安全、环保与成本之间的对立统一关系。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]