[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908768":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908768,587,1,"单选题","下列关于工程项目目标控制方法的表述中正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","直方图是一种用来寻找影响工程质量主要因素的有效工具",false,{"key":16,"text":17,"correct":14},"B","通过因果分析图，可以发现工程项目中的主要质量问题",{"key":19,"text":20,"correct":21},"C","S 曲线与香蕉曲线都可以用来控制工程造价和工程进度",true,{"key":23,"text":24,"correct":14},"D","控制图法和直方图法分别属于质量控制的静态和动态分析方法","2020版教材页码：P103~105。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]