[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908763":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},908763,587,1,"单选题","评价计算期不同的互斥方案的经济效果时，可采用的动态评价方法有（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","增量投资收益率法和净现值法",false,{"key":16,"text":17,"correct":18},"B","增量内部收益率法和净年值法",true,{"key":20,"text":21,"correct":14},"C","增量投资回收期法和净年值法",{"key":23,"text":24,"correct":14},"D","年折算费用法和年费用现值法","2020版教材页码：P189~192",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]