[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908736":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908736,587,1,"单选题","在工程寿命周期成本分析中，进行系统设置费与该系统开发、设置所用全部时间之间的权衡分析时所采用的主要方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计划评审技术",true,{"key":16,"text":17,"correct":18},"B","价值分析法",false,{"key":20,"text":21,"correct":18},"C","赢得值分析法",{"key":23,"text":24,"correct":18},"D","因素分析法","2020版教材页码：P225。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]