[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908725":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908725,587,1,"单选题","下列偏差分析方法中，既可分析费用偏差，又可分析进度偏差的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","时标网络图和曲线法",true,{"key":16,"text":17,"correct":18},"B","曲线法和控制图法",false,{"key":20,"text":21,"correct":18},"C","排列图法和时标网络图法",{"key":23,"text":24,"correct":18},"D","控制图法和表格法","2020版教材页码：P358~359",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]