[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908723":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908723,587,1,"单选题","某工程经偏差分析得到费用绩效指数CPI﹥1，进度绩效指数SPI＜1，则表明（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程费用超支",false,{"key":16,"text":17,"correct":14},"B","工程进度提前",{"key":19,"text":20,"correct":14},"C","已完工程计划费用＜已完工程实际费用",{"key":22,"text":23,"correct":24},"D","拟完工程计划费用﹥已完工程计划费用﹥已完工程实际费用",true,"本题考查的是工程费用的动态监控。CPI=已完工程计划费用\u002F已完工程实际费用﹥1，已完工程计划费用﹥已完工程实际费用，证明工程费用节约；SPI=已完工程计划费用\u002F拟完工程计划费用＜1，已完工程计划费用＜拟完工程计划费用，说明工程进度拖后；拟完工程计划费用﹥已完工程计划费用﹥已完工程实际费用。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]