[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908722":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},908722,587,1,"单选题","某工程施工至2014 年7 月底，已完工程计划费用(BCWP)为600 万元，已完工程实际费用(ACWP)为800 万元，拟完工程计划费用(BCWS)为700 万元，则该工程此时的偏差情况是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","费用节约，进度提前",false,{"key":16,"text":17,"correct":18},"B","费用超支，进度拖后",true,{"key":20,"text":21,"correct":14},"C","费用节约，进度拖后",{"key":23,"text":24,"correct":14},"D","费用超支，进度提前","费用偏差(CV)=已完工程计划费用(BCWP)-已完工程实际费用(ACWP)。当 CV>0 时，说明工程费用节约;当 CV 0 时，说明工程进度超前;当 SV\u003C0时，说明工程进度拖后。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]