[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908719":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908719,587,1,"单选题","其工程施工至2016 年12 月底，已完工程计划费用（BCWP）2000 万元，拟完工程计划费用（BCWS）2500 万元，已完工程实际费用（ACWP）为1800 万元，则此时该工程的费用绩效指数CPI 为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","0.8",false,{"key":16,"text":17,"correct":14},"B","0.9",{"key":19,"text":20,"correct":21},"C","1.11",true,{"key":23,"text":24,"correct":14},"D","1.25","费用绩效指数（CPI）=已完工程计划费用（BCWP）\u002F已完工程实际费用（ACWP）=2000\u002F1800=1.11",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]