[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908711":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908711,587,1,"单选题","下列关于不平衡报价法的说法中，错误的说法是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","能够早日结算的项目，可以适当的提高报价，后期工程项目的报价可适当降低",false,{"key":16,"text":17,"correct":14},"B","经核算，预计今后工程量会增加的项目，可适当提高报价",{"key":19,"text":20,"correct":21},"C","设计图纸不明确、估计修改后工程量要增加的项目，应适当降低单价",true,{"key":23,"text":24,"correct":14},"D","单价与包干混合制合同中，招标人要求有些项目采用包干报价时，宜报高价","本题考查的是施工投标报价策略。选项 C 错误，设计图纸不明确、估计修改后工程量要增加的，可以提高单价；而工程内容说明不清楚的，则可降低一些单价，在工程实施阶段通过索赔再寻求提高单价的机会。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]