[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908675":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908675,587,1,"单选题","某工程有甲乙丙丁四个实施方案可供选择，四个方案的投资额依次是60 万元、80 万元、100 万元、120 万元。年运行成本依次是16 万元、13 万元、10 万元和6 万元，各方案应用环境相同。设基准投资率为10%。则采用折算费用法选择的最优方案为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","丁",true,{"key":16,"text":17,"correct":18},"B","甲",false,{"key":20,"text":21,"correct":18},"C","乙",{"key":23,"text":24,"correct":18},"D","丙","甲方案的折算费用=16+60×10%=22 万元；乙方案的折算费用=13+80×10%=21 万元；丙方案的折算费用=10+100×10%=20 万元；丁方案的折算费用=6+120×10%=18 万元。最优的方案为折算费用最小的方案。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]