[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908650":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},908650,587,1,"单选题","某工程双代号时标网络计划如下图所示，其中工作B 的总时差和自由时差（ ）周。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","均为1",false,{"key":16,"text":17,"correct":18},"B","分别为2 和1",true,{"key":20,"text":21,"correct":14},"C","分别为4 和1",{"key":23,"text":24,"correct":14},"D","均为4","本题考查的是双代号时标网络计划。TFB=1+1=2，FFB=1。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]