[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908646":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908646,587,1,"单选题","在某工程双代号网络计划中，工作M 的最早开始时间和最迟开始时间分别为第15 天和第18 天，其持续时间为7 天。该工作有两项紧后工作，它们的最早开始时间分别为第24 天和第26 天，则工作M 的总时差和自由时差分别为（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","分别为4 和0",false,{"key":16,"text":17,"correct":14},"B","均为3",{"key":19,"text":20,"correct":21},"C","分别为3 和2",true,{"key":23,"text":24,"correct":14},"D","均为2","本题考查的是时间参数的基本概念。总时差为：18-15=3（天）；自由时差：24-7-15=2（天）",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]