[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908643":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908643,587,1,"单选题","某分部工程双代号网络计划如下图所示，节点中下方数字为该工作的持续时间（单位：天），其关键线路有（ ）条。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","2",{"key":19,"text":20,"correct":14},"C","3",{"key":22,"text":23,"correct":24},"D","4",true,"本题考查的是网络图的绘制。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]