[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908642":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908642,587,1,"单选题","已知某工作总时差为8 天，最迟完成时间为第16 天，最早开始时间为第7 天，则该工作的持续时间为（ ）天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","8",false,{"key":16,"text":17,"correct":14},"B","7",{"key":19,"text":20,"correct":14},"C","4",{"key":22,"text":23,"correct":24},"D","1",true,"因为总时差=最迟完成时间-最早完成时间。已知总时差为 8 天，最迟完成时间为第 16 天，则最早完成时间为 8 天 。因为最早完成时间=最早开始时间+本工作的持续时间，且最早开始时间为第 7 天，则本工作的持续时间为 1 天。所以，正确选项为 D。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]