[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908641":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908641,587,1,"单选题","某工程有3 个施工过程，分为3 个施工段组织流水施工。3 个施工过程的流水节拍以此为3、3、4 天，5、2、1 天和4、1、5 天，则流水施工工期为（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","6",false,{"key":16,"text":17,"correct":14},"B","17",{"key":19,"text":20,"correct":21},"C","18",true,{"key":23,"text":24,"correct":14},"D","19","用大差法求出流水步距分别为 3、5，最后一个施工过程施工了 4+1+5=10 天，没有间歇、搭接和插入，故流水施工工期=3+5+10=18 天。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]