[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908637":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},908637,587,1,"单选题","某分部工程划分为4 个施工过程、3 个施工段，组织加快的成倍节拍流水施工，如果流水节拍分别为6、4、4、2 天，则流水步距为（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":18},"B","2",true,{"key":20,"text":21,"correct":14},"C","4",{"key":23,"text":24,"correct":14},"D","6","流水步距为 6、4、4、2 的最大公约数等于 2 天。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]