[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908631":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},908631,587,1,"单选题","某工程组织成倍节拍流水施工， 4 个施工段， 4 个施工过程的流水节拍分别为5 ，10，10，15，则该工程的流水工期为（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","50",false,{"key":16,"text":17,"correct":18},"B","55",true,{"key":20,"text":21,"correct":14},"C","60",{"key":23,"text":24,"correct":14},"D","70","首先计算流水步距为流水节拍的最大公约数为 5 ，然后计算各施工过程所需的施工队数为 1，2 ，2 ， 3 ，最后计算流水工期=[4+（1+2+2+3） -1]×5=55 (天)。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]