[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908630":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908630,587,1,"单选题","某工程按全等节拍流水组织施工，共分4 道施工工序，3 个施工段，估计工期为72 天，则其流水节拍应为（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","6",false,{"key":16,"text":17,"correct":14},"B","9",{"key":19,"text":20,"correct":21},"C","12",true,{"key":23,"text":24,"correct":14},"D","18","T=（m+n-1）×t=（3+4-1）×t=72，得 t=12 天。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]