[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908586":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908586,587,1,"单选题","某项目中建筑安装工程费用为560 万元，设备和工、器具购置费工为330 万元，工程建设其他费用为133 万元，基本预备费为102 万元，涨价预备费55 万元，建设期贷款利息为59 万元，则动态投资为（ ）万元。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1023",false,{"key":16,"text":17,"correct":14},"B","1125",{"key":19,"text":20,"correct":14},"C","1180",{"key":22,"text":23,"correct":24},"D","1239",true,"建设项目动态投资包括静态投资、涨价预备费、建设期贷款利息。静态投资包括建筑工程安装费用，设备和工、器具购置费，工程建设其他费用，基本预备费。故动态投资=560+330+133+102+55+59=1239 万元。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]