[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908578":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908578,587,1,"单选题","（2019年）工程竣工结算审查时，对变更签证凭据审查的主要内容是其真实性、合法性和（）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","严密性",false,{"key":16,"text":17,"correct":14},"B","包容性",{"key":19,"text":20,"correct":14},"C","可行性",{"key":22,"text":23,"correct":24},"D","有效性",true,"施工承包单位内部审查工程竣工结算的内容中包括，审查变更签证凭据的真实性、合法性、有效性，核准变更工程费用。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]