[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908576":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},908576,587,1,"单选题","（2017 年考题）关于工程质量保证金，下列说法中正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","质量保证金总预留比例不得高于签约合同价的5%",false,{"key":16,"text":17,"correct":18},"B","已经缴纳履约保证金的，不得同时预留质量保证金",true,{"key":20,"text":21,"correct":14},"C","采用工程质量保证担保的，预留质量保证金不得高于合同价的2%",{"key":23,"text":24,"correct":14},"D","质量保证金的返还期限一般为2 年","发包人应按照合同约定方式预留质量保证金，质量保证金总预留比例不得高于工程价款结算总额的 5%。合同约定由承包人以银行保函替代预留质量保证金的，保函金额不得高于工程价款结算总额的 5%。在工程项目竣工前，已经缴纳履约保证金的，发包人不得同时预留工程质量保证金。采用工程质量保证担保、工程质量保险等其他方式的，发包人不得再预留质量保证金。缺陷责任期内，承包人认真履行合同约定的责任，到期后，承包人向发包人申请返还质量保证金。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]