[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908569":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},908569,587,1,"单选题","（2019年）按工程进度编制施工阶段资金使用计划,首要进行的工作是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计算单位时间的资金支出目标",false,{"key":16,"text":17,"correct":18},"B","编制工程施工进度计划",true,{"key":20,"text":21,"correct":14},"C","绘制资金使用时间进度计划S曲线",{"key":23,"text":24,"correct":14},"D","计算规定时间内累计资金支出额","按照工程进度编制资金使用计划：1、编制工程施工进度计划 2、计算单位时间的资金支出目标 3、计算规定时间内的累计资金支出额。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]