[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908567":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908567,587,1,"单选题","（2019年）工程施工过程中，对于施工承包单位要求的工程变更。施工承包单位提出的程序是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","向建设单位提出书面变更请求，阐明变更理由",false,{"key":16,"text":17,"correct":14},"B","向设计单位提出书面变更建议，并附变更图纸",{"key":19,"text":20,"correct":14},"C","向监理人提出书面变更通知，并附变更详情",{"key":22,"text":23,"correct":24},"D","向监理人提出书面变更建议，阐明变更依据",true,"施工承包单位收到监理人按合同约定发出的图纸和文件，经检查认为其中存在属于变更范围的情形，如提高工程质量标准、增加工作内容、改变工程的位置或尺寸等，可向监理人提出书面变更建议。变更建议应阐明要求变更的依据，并附必要的图纸和说明。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]