[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908566":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908566,587,1,"单选题","(2018年)某工程施工至月底时的情况为:已完工程量120m.实际单价8000 元\u002F，计划工程量100,计划单价7500 \u002Fm,则工程量在月底的费用偏差为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","超支6 万元",true,{"key":16,"text":17,"correct":18},"B","节约6 万元",false,{"key":20,"text":21,"correct":18},"C","超支15 万元",{"key":23,"text":24,"correct":18},"D","节约15 万元","费用偏差（CV）=已完工程计划费用（BCWP）-已完工程实际费用（ACWP）=120×7500-120×8000=120×（7500-8000）=-60000 元=-6 万元＜0，故费用超支。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]