[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908562":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908562,587,1,"单选题","（2017年考题）其工程施工至2016 年12 月底,已完工程计划用2000 万元,拟完工程计划费用2500 万元,已完工程实际用为1800 万元,则此时该工程的费用绩效指数CPI 为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","0.8",false,{"key":16,"text":17,"correct":14},"B","0.9",{"key":19,"text":20,"correct":21},"C","1.11",true,{"key":23,"text":24,"correct":14},"D","1.25","考查工程费用的动态监控（赢得值法），常规考查。只要会三个参数，就可以做对该题，不需要记忆谁减去谁，或谁除以谁。 三个参数： 拟完工工程计划费用（2500） 已完工程计划费用（2000） 已完工程实际费用（1800） 2000\u002F1800=1.11",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]