[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908559":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908559,587,1,"单选题","(2015年)根据《建设工程价款结算暂行办法》，对于施工承包单位超交的金额为6000万元的工程竣工结算报告，建设单位的审查时限是()天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","30",false,{"key":16,"text":17,"correct":14},"B","45",{"key":19,"text":20,"correct":21},"C","60",true,{"key":23,"text":24,"correct":14},"D","90","本题考查的是工程价款结算及其审查。5000万以上的审查时限是60天。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]