[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908556":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908556,587,1,"单选题","(2013年)根据《标准施工招标文件》，由施工承包单位提出的索赔按程序得到了处理，且施工单位接受索赔处理结果的，建设单位应在作出索赔处理答复后()天内完成赔付。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","14",false,{"key":16,"text":17,"correct":14},"B","21",{"key":19,"text":20,"correct":21},"C","28",true,{"key":23,"text":24,"correct":14},"D","42","该题主要考察的是：监理人处理索赔的程序。施工承包单位接受索赔处理结果的，建设单位应在作出索赔处理结果答复后28天内完成赔付。施工承包单位不接受索赔处理结果的，按合同中争议解决条款的约定处理。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]