[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908553":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},908553,587,1,"单选题","(2013年)按工程进度绘制的资金使用计划S曲线必然包括在&ldquo;香蕉图&rdquo;内，该&ldquo;香蕉图&rdquo;是由工程网络计划中全部工作分别按()绘制的两条S曲线组成。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","最早开始时间(ES)开始和最早完成时间(E F)完成",false,{"key":16,"text":17,"correct":18},"B","最早开始时间(ES)开始和最迟开始时间(LS)开始",true,{"key":20,"text":21,"correct":14},"C","最迟开始时间(LS)开始和最早完成时间(E完成",{"key":23,"text":24,"correct":14},"D","最迟开始时间(LS)开始和最迟完成时间(L完成","S曲线(投资计划值曲线)必然包括在由全部工作均按最早开始时间(ES)开始和全部工作均按最迟开始时间(LS)开始的曲线所组成的&ldquo;香蕉图&rdquo;内，如图6.4.1所示。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]