[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908548":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908548,587,1,"单选题","(2015年)为核算施工成本，施工项目经理部应建立和健全以()为对象的成本核算财务体系。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","单位工程",true,{"key":16,"text":17,"correct":18},"B","单项工程",false,{"key":20,"text":21,"correct":18},"C","分部工程",{"key":23,"text":24,"correct":18},"D","分项工程","本题考查的是施工成本管理。施工项目经理部应建立和健全以单位工程为对象的成本核算账务体系，严格区分企业经营成本和项目生产成本，在工程项目实施阶段不对企业经营成本进行分摊，以正确反映工程项目可控成本的收、支、结、转的状况和成本管理业绩。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]