[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908546":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},908546,587,1,"单选题","(2014年)某工程施工至2014年7月底，已完工程计划费用（BCWP）为600万元，已完工程实际费用（ACWP）为800万元，拟完工程计划费用（BCWS）为700万元，则该工程此时的偏差情况是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","费用节约，进度提前",false,{"key":16,"text":17,"correct":18},"B","费用超支，进度拖后",true,{"key":20,"text":21,"correct":14},"C","费用节约，进度拖后",{"key":23,"text":24,"correct":14},"D","费用超支，进度提前","该题主要考察的是：合同计价方式，费用偏差（CV）=已完工程计划费用（BCWP）-已完工程实际费用（ACWP）；当CV＞0时，说明工程费用节约；当CV＜0时，说明工程费用超支。进度偏差（SV）=已完工程计划费用（BCWP）-拟完工程计划费用（BCWS）；当SV＞0时，说明工程进度超前；当SV＜0时，说明工程进度拖后。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]