[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908545":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},908545,587,1,"单选题","(2014年)施工成本核算中，固定资产折旧的起算时间和计提方式分别是固定资产投入使用的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","当月起，按月计提",false,{"key":16,"text":17,"correct":18},"B","次月起，按月计提",true,{"key":20,"text":21,"correct":14},"C","单月起，按年计提",{"key":23,"text":24,"correct":14},"D","次月起，按年计提","该题主要考察的是：成本核算，固定资产折旧从固定资产投入使用月份的次月起，按月计提。停止使用的固定资产，从停用月份的次月起，停止计提折旧。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]