[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908543":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908543,587,1,"单选题","(2010年)在工程项目成本管理中，由进度偏差引起的累计成本偏差可以用()差值度量。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","已完工程预算成本与拟完工程预算成本",true,{"key":16,"text":17,"correct":18},"B","已完工程预算成本与已完工程实际成本",false,{"key":20,"text":21,"correct":18},"C","已完工程实际成本与拟完工程预算成本",{"key":23,"text":24,"correct":18},"D","已完工程实际成本与已完工程预算成本","通过比较已完工程预算成本与拟完工程预算成本之间的差值，可以分析由于进度偏差而引起的累计成本偏差。并通过计算后续未完工程的计划成本余额，预测其尚需的成本数额，从而为后续工程施工的成本、进度控制及寻求降低成本挖潜途径指明方向。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]