[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908541":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},908541,587,1,"单选题","(2012年)下列方法中，可用于编制工程项目成本计划的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","净值分析法",false,{"key":16,"text":17,"correct":18},"B","目标利润法",true,{"key":20,"text":21,"correct":14},"C","工期—成本同步分析法",{"key":23,"text":24,"correct":14},"D","成本分析表法","(2）成本计划的编制方法。 1）目标利润法。2）技术进步法。3）按实计算法。4）定率估算法（历史资料法）。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]