[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908540":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},908540,587,1,"单选题","(2013年)在工程费用监控过程中，明确费用控制人员的任务和职责分工，改善费用控制工作流程等措施，属于费用偏差纠正的()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","合同措施",false,{"key":16,"text":17,"correct":14},"B","技术措施",{"key":19,"text":20,"correct":14},"C","经济措施",{"key":22,"text":23,"correct":24},"D","组织措施",true,"该题主要考察的是：费用偏差的纠正措施。组织措施。是指从费用控制的组织管理方面采取的措施，包括：落实费用控制的组织机构和人员，明确各级费用控制人员的任务、职责分工，改善费用控制工作流程等。组织措施是其他措施的前提和保障。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]