[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908530":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},908530,587,1,"单选题","（2019年）合同价格的准确数据只有在（ ）后才能确定。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","后续工程不再发生工程变更",false,{"key":16,"text":17,"correct":18},"B","承包人完成缺陷责任期工作",true,{"key":20,"text":21,"correct":14},"C","工程审计全部完成",{"key":23,"text":24,"correct":14},"D","竣工结算价支付完成","缺陷责任期终止证书签发后，承包人可按专用合同条款约定的份数和期限向监理人提交最终结清申请单，并提供相关证明材料。发包人对最终结清申请单内容有异议的，有权要求承包人进行修正和提供补充资料，由承包人向监理人提交修正后的最终结清申请单。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]