[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908529":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},908529,587,1,"单选题","（2019年）发包人最迟应当在监理人收到进度付款申请单的（ ）天内，将进度应付款支付给承包人。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","14",false,{"key":16,"text":17,"correct":14},"B","21",{"key":19,"text":20,"correct":21},"C","28",true,{"key":23,"text":24,"correct":14},"D","35","发包人最迟应在监理人收到进度付款申请单后的28天内，将进度应付款支付给承包人。发包人未能在前述时间内完成审批或不予答复的，视为发包人同意进度付款申请。发包人不按期支付的，按专用合同条款的约定支付逾期付款违约金。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]