[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-908527":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},908527,587,1,"单选题","（2017年考题）下列不同计价方式的合同中,建设单位最难控制工程造价的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本加百分比酬金合同",true,{"key":16,"text":17,"correct":18},"B","单价全同",false,{"key":20,"text":21,"correct":18},"C","目标成本加奖罚合同",{"key":23,"text":24,"correct":18},"D","总价合同","表6.3.2，成本加百分比酬金合同对于建设单位造价控制难度最大。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理","建筑工程",0]